Turbine/Generator Project

Counce, TN

Industry: Hydro/Power Generation

Project Scope

The Turbine/Generator project required CR Meyer to demolish the existing Salt Cake Towers followed by the construction of the EPC Buildings, Cooling Tower Foundation, Pipe Bridge & Foundation, Piping, and the Electrical Instrumentation. CR Meyer installed Steam, Condensate, Air, Mill Water, Cooling Water Piping, Turbine/Generator on Foundations, Condenser Hot Well Pumps, the Lube Oil Pump System, and Coolers. The final phase included the installation of the Cooling Tower Circulation Pumps as well as the assembly and attachment of the Condenser Turbine Generator Set.

Project Stats

  • Peak Employees on-site: 60
  • No. of Contracts: 4
  • Duration: 9 Months
8 days after start-up - the Paper Machine has safely achieved the five-day average end-of-curve rates for yield, waste, and uptime 20 days ahead of the start-up curve! This is a huge accomplishment and we cannot thank you enough for your contributions.
Paper Industry Customer